Delivery and Storage of Pre-fabricated Structures

Structural units are delivered to erection zones by most effective mechanised procedures and allowing for haulage distance, availability of approach roads and conditions of in-site roads. Depending on the character of application of structural units, they are transported from the place of manufacturing to construction sites and unloaded at a pre-assembly area. Pre-assembly area is a site storage area or a zone identified in an erecting area.

Pre-fabricated structural units are generally transported by trucks with two-axle trailers, tractor trucks with semi-trailers and panel transporters. Delivered units to the construction site should correspond to assembly lists which specify the name, the type and the number of pre-fabricated elements intended for placement in a specified area of the building.