Before starting construction of a residential building, a site has to be owned at a desired place. A plan to be prepared as per the need of the person and necessary approval has to be obtained. The site clearance has to be done and then the actual work has to be started. The sequence of operations is discussed below.
Step 1: Excavation of foundation
Step 2: Base concrete
Step 3: Masonry construction
Step 4: Plinth beam construction
Step 5: Sand filling up to plinth level
Step 6: Preparation of doors and windows
Step 7: Floor concrete
Step 8: Starting of superstructure construction
Step 9: Fixing doors and windows
Step 10: Finishing superstructure upto lintel level
Step 11: Construction of lintels and sunshades
Step 12: Brickwork up to ceiling and roof
Step 13: Electrical pipe and board fixing
Step 14: Roof casting
Step 15: Removal of formwork
Step 16: Finishing all plumbing work
Step 17: Plastering
Step 18: Floor finishing
Step 19: Construction of compound or boundary walls
Step 20: Fixing doors and window shutters
Step 21: Electrical fittings
Step 22: Painting and polishing.
Above discussed sequence of operations is shown in a flow diagram, Fig. 14.2.

Figure 14.2 Construction sequence of residential building